All buildings
The buildings
Staff Housing
Construction status43%
Under construction
- Block AStructure under way35%
- Block BStructure complete50%
Overall progress of the Külliye: 9%
Last updated:

News about this building
Housing · Block B: concrete work is complete; brickwork and plastering are next
Housing · Block A: concrete for the second floor has been poured
All buildings
- Digital Presentation and Education Centre Not started 0%View building
- International Institutes of Specialisation Under construction 12%View building
- Siyer-i Nebî Youth Camp Centres Under construction 4%View building
- Ashab al-Suffa Centre and Institute of Tasawwuf Not started 0%View building
- Kırklar Mosque Under construction 15%View building
- Refectory and Tea House Not started 0%View building
- Siyer Garden Nursery and Childcare Units Not started 0%View building
- Administrative Building Plinth level reached 20%View building